How trial areas establish production parameters

A ground improvement design is a prediction until it is tested. In the trial area the proposed parameters are applied to part of the site and the result is measured, and the parameters for full production are then fixed and agreed.

By the GEODEN technical team · Published

Why a trial is needed

Ground response depends on soil type, density, fines content and groundwater, all of which vary. A trial replaces assumptions with measurements before the whole site is treated. That reduces risk for the client, the consultant and the contractor.

What a trial includes

  • A location that represents the site and, where conditions vary, its most difficult part.
  • Baseline tests before treatment, such as CPT.
  • Treatment using the proposed parameters, sometimes with more than one spacing or energy level.
  • Measurement of the ground response during treatment.
  • Tests after treatment at the same positions, compared with the baseline and the acceptance criteria.

What is measured, by method

MethodResponse measured during the trial
Dynamic CompactionCrater depth after each drop, heave around the print, induced settlement
Rapid Impact CompactionFoot penetration per blow and total penetration per point
High Energy Impact CompactionSurface settlement against number of passes
Vibro CompactionVibrator power and holding time per stage, at different point spacings

What the trial delivers

  • Production parameters: energy, spacing, number of drops, blows or passes.
  • Stopping criteria that can be checked at every point.
  • The verification regime: which tests, where, and how long after treatment.

These are recorded in a trial report and agreed with the consultant before production starts.

When to repeat it

If the ground changes across the site (a different fill, a higher water table, more fines), the original trial may no longer apply, and a further trial in the new conditions is justified.